DAILONG (2x50 kW) MICRO-HYDEL PROJECT, Tamenglong District
PROJECT AT A GLANCE
1. Project title : Dailong Micro Hydel Project (2 x 50) kW, Dailong Village, Tamenglong District, Manipur.
2. Broad discipline : Multi Engineering Discipline covering Civil, Electrical, Electronics and Mechanical Engineering.
3. Project cost : Rs. 1,01,25,819/-
i) DST, GoI Share : Rs 91,13,237/-
ii) State Share : Rs 10,12,582/-
4. Implementing agency : Manipur Science & Technology Council Central jail Road, Imphal – 795001.
5. Sponsoring agencies : i) S&T Council Division, DST, GOI ,
ii) DST, Govt. of Manipur
1.0 Abstract of the Project:
Micro Hydel Power Generation is a viable alternative to extension of grid lines in rural/remote/hilly areas. To exploit micro hydel potential on large scale, it is necessary to develop cross-flow turbine suitable for (2 x 50) kW and more for installation on the rivers/streams in the hills.. Since there is a very good perennial source of water in the Zoulangpang river, Dailong Village, Tamenglong District, therefore cross-flow turbine is an ideal option to meet the site conditions in the implementation of such schemes in the State of Manipur
2.0 Project Site :
The project was implemented at Dailong village, Tamenglong District, Manipur over the Zoulangpang Stream. Dailong viallage is situated at about 160 km from the State Capital, Imphal and 12 kms from Tamenglong District Headquarters towards Tamei in the Tamenglong-Tamei Road.
2.1 Village Details :
i) Village : Dailong
ii) Block : Tamenglong
iii) District : Tamenglong
iv) State : Manipur
v) Height above M.S.L. : 1055 m
vi) Total Population :1860
vii) Total Households : 130
viii) Total Geographical Area : 32 Ha
ix) Total cropped area : 51 Ha
x) Total irrigated area : Rainfed
xi) Motorable Road : Right upto the village
xii) Stream/River : Zoulangpang
xiii) Electricity Line : Very erratic, very low voltage electricity from
State Electricity Dept.
xix) Sub health centre : At the village
xv) School : 1(One) Primary School
xvi) Tank/Pond : Nil
xvii) Well : Nil
xviii) Post office : at Tamenglong H.Q.
xix) Market : at Tamenglong H.Q.
xx) Police Station : at Tamenglong H.Q.
2.2 Details of the Stream :
i) Name of the stream : Zoulangpang
ii) Months during which
water flows : Perrennial (Peak period : May-November)
iii) Average discharge : 180 lps
iv) Catchment area : 4.75 sq.km.
3.1 Design Parameters:
3.2 Power generation:
i) Installed capacity : 2x50 kW
ii) Power (potential)
Generation (based : 80 kW.
on 80% efficiency)
iii) Actual Power Generated : 96 kW
3.3 Cost of generation : Rs. 1.28/kW
4.0 Project Summary :
The project was started on March 31, 2000 and commissioned during February, 2010. The project was inaugurated on the 20th September, 2010 by Shri L.P. Gonmei, Principal Secretary (Power), Govt. of Manipur with a formal Inaugural Function presided over by Shri H. Imocha Singh, Commissioner (Science & Technology), Govt. of Manipur. Shri K. Panmei, Deputy Commissioner, Tamenglong District was the Honour Guest of the Function. Various officials from Tamenglong District Headquarter and State Power Department also attended the Inaugural Function.
| Dev. of Technology | Manipur at a Glance | Industrial Scenario | Market Organisation | Natural Resources | Human Resource |
| Technology sources | Technology for transfer by MASTEC | Local Technology in Manipur | Banking and Finance | Grant makers |
| Entrepreneurship development | Industrial Consultancy of NE | State Govt. Departments | Other useful websites |
| Contact us | About TBIS | About MASTEC | Current News | Home |